2.16 m VHF: Channel 69 Report an Incident

News - 03/07/15

Cowes Breakwater special project review

The CHC Commissioners met on Friday, 3rd July for an Extraordinary Board Meeting to consider the formal Cowes Breakwater Project review that addressed the issues of changes in tidal flows and potential changes to the sedimentation regime as a result of the 2014 breakwater construction. The Commissioners received a presentation from their consultant hydrodynamic engineers, and after careful and detailed consideration, unanimously agreed to proceed with the scheduled 2015 breakwater construction and the placement of the rock armour.  

Cowes Harbour Commission (CHC) has informed harbour users of the changes to tidal flows that occurred after the construction of the Cowes Breakwater gravel core in September 2014. The extensive pre-breakwater construction tidal modelling carried out did predict certain changes to the tidal rates and directions within the harbour, but CHC recognises that differences have been noted between the predicted modelling outputs and actual flows observed and recorded. In addition, concerns have been raised by a number of harbour users regarding potential increased levels of siltation occurring within the harbour. The Commissioners understand the concerns of stakeholders and CHC’s responsibility for the successful delivery of the Cowes Breakwater Project.

CHC has carried out a continuous process of review throughout the Cowes Breakwater Project; this continues. Further information acquired from the ongoing review with CHC’s consultant hydrodynamic engineers ABPmer and project managers Atkins has delivered an updated understanding of the differences between the modelled tides and observed tidal changes and enabled CHC to look at potential changes to sedimentation.

As a result, CHC determined it would be appropriate to carry out a full and formal “special project review” to provide the best available advice for the Board to consider and inform the decision on whether to proceed with or delay the 2015 breakwater construction.

Harbour Advisory Committee representatives were present at both CHC’s June and the Extraordinary July Board meetings to ensure that stakeholders are kept fully informed and involved in the review. CHC’s project and government funding partner the Homes and Communities Agency (HCA) has been consulted throughout and also attended the June Board meeting.

CHC presented information on tidal and sedimentation issues to the Advisory Committee at their meeting on 23rd June including information on the data, surveys and modelling evidence. The decision required – to proceed or to delay the breakwater works – was considered including associated risks and wider impacts. The Advisory Committee concluded that there was not enough evidence to warrant a delay and supported continuing with the next stage of breakwater construction.

The Commissioners agreed at the Extraordinary meeting, the importance of completing the new hydrodynamic model and its use in reviewing the design optimisation of the next phases of the Cowes Breakwater Project. The next phases being the dredging of the new Eastern Channel and extension of the Shrape breakwater. They also confirmed their intention to continue to consult all stakeholders as information becomes available and their commitment to another formal project review and stakeholder consultation before finalising any decisions on the next phases of the project.

CHC will provide the background information and advice that formed the basis of the best available evidence at this current time to make this important decision to proceed with the Cowes Breakwater Project in the interests of all stakeholders.